Full execution of one of the three chambers that make up the Sluice of the Pacific, including the area of lock-gates. The work contracted by Tecozam consists fundamentally in the formwork of 550,000.00 m2 in climbing walls, slabs and foundations and 750,000 m3 of structural concrete. Apart from the formwork and concreting work, TECOZAM performs specific works of joints treatment with high-pressure machine, curing of concrete and arrangement of metallic embedded elements that will receive the mobile teams of the canal.
Works will be developed 24 hours a day from Monday to Saturday, with teams led by expert trainers in climbing formwork and local workers.