Works description:
Execution of a dam of loose materials downstream of the existing gravity dam to heighten the water sheet of the reservoir.
Works performed:
TecoZam has been entrusted to build the waterproofing dam, it is located upstream of the new dam and is born from the old one.
The works carried out, formwork and concrete pouring, are carried out with a sliding formwork system with which it is possible to get continius concrete pouring of 15 m width and 0.3 m thick and length, in this case, up to 90 m.